💰
Mechanic's Lien Basics and Constitutional Origin
financing Persons furnishing labor or material to improve real estate may file a lien if not timely paid. The basic right arises from Article XIV, Section 3 of the California Constitution, implemented by Civil Code Title 15 (Section 3082 et seq.). The lien's theory is that improvements add value, so it is equitable to charge the land.
Key Rules
- ✓Mechanics, materialmen, artisans and laborers have a constitutional lien right (Art. XIV, Sec. 3)
- ✓The lien must be founded on a valid contract and is valid only to the extent of labor/materials actually used
- ✓No lien attaches to a public work; only to private works of improvement
💰
Steps to Convert a Mechanic's Lien to Money
financing Converting the lien to payment requires: (1) timely recordation of a notice and claim of lien in the county where the work is located; (2) perfection by filing a lawsuit in the proper court; (3) recording a lis pendens; (4) timely pursuit of the lawsuit to judgment; and (5) enforcement by a foreclosure sale.
Key Rules
- ✓A claim of lien must be timely recorded, then a foreclosure action filed to perfect it
- ✓A lis pendens must be recorded to give notice of the pending lawsuit
- ✓Failure to sue within 90 days after recording renders the lien null and void
💰
Preliminary 20-Day Notice
financing Except claimants under direct contract with the owner, one performing labor for wages, or an express labor trust fund, a claimant must serve a preliminary 20-day notice within 20 days of first furnishing labor/materials (Civil Code 3097). It is a prerequisite to a valid mechanic's lien and informs the owner, contractor, and lender that liens may arise.
Key Rules
- ✓The preliminary 20-day notice must be given no later than 20 days after first furnishing labor/materials
- ✓It is a prerequisite to the validity of a claim of mechanic's lien
- ✓Direct-contract claimants notify only the construction lender; others notify owner, contractor, and lender
- ✓A current statutory form must be used or the court may disregard the notice
💰
Time Limits for Recording a Claim of Lien
financing With a recorded notice of completion/cessation, an original contractor must record within 60 days; any other claimant within 30 days. If no notice of completion/cessation is recorded, any claimant has 90 days after completion to record the claim of lien.
Key Rules
- ✓Original contractor: 60 days after notice of completion/cessation
- ✓Other claimants: 30 days after notice of completion/cessation
- ✓No notice recorded: 90 days after completion for all claimants
💰
Termination of Lien; Lender's Priority
financing A mechanic's lien terminates by voluntary release or automatically if no foreclosure action is filed within 90 days of recording. If work commenced before the lender recorded its deed of trust, all mechanics' liens are prior to the lender's encumbrance (Civil Code 3134), jeopardizing construction loan security.
Key Rules
- ✓Foreclosure action must be filed within 90 days after recording the lien or it is void
- ✓If work commenced before the deed of trust was recorded, mechanics' liens take priority over the lender
- ✓Extended credit for lien purposes may not exceed one year from completion, and notice must be filed within the 90-day period
💰
Determination of Completion and Notice of Completion
financing Completion is fixed by: occupation/use plus cessation of labor; owner's acceptance; cessation of labor for 60 continuous days; or cessation of 30 days with a recorded notice of cessation. The owner may file a notice of completion within 10 days of completion. A public-entity work is complete on acceptance or 30 days' cessation.
Key Rules
- ✓Completion may occur by acceptance, occupation with cessation, 60-day cessation, or 30-day cessation with recorded notice
- ✓A notice of completion should be recorded within 10 days after completion (Civil Code 3093, 3117)
💰
Notice of Nonresponsibility and Release Bond
financing An owner (or interest holder) may avoid liability by posting a notice of nonresponsibility in a conspicuous place and recording a verified copy within 10 days of learning of the work. Owners/contractors disputing a lien may record a lien release bond (Civil Code 3143) to lift the lien from the property.
Key Rules
- ✓A notice of nonresponsibility must be posted AND recorded within 10 days of obtaining knowledge of the work
- ✓If posting is not done, a recorded notice affords no protection
- ✓A recorded lien release bond lifts the claim of lien from the property (Civil Code 3143)
💰
Design Professional's Lien
financing Effective 1991, architects, registered engineers, and licensed land surveyors under written contract may file a design professional's lien (Civil Code 3081.1–3081.10). A 10-day written demand for payment must be mailed before recording. The lien does not apply to single-family owner-occupied residences under $100,000 and yields to prior recorded interests.
Key Rules
- ✓A 10-day written demand for payment (certified/registered mail) must precede recording
- ✓The lien does not apply to single-family owner-occupied residences under $100,000 (Civil Code 3081.10)
- ✓The lien does not take priority over interests recorded before it (Civil Code 3081.9)